Critical Path
A colleague of mine recently asked what I meant by "critical path." I gave her the following example, which she suggested I share:
"Critical path" is a project management term. It represents the longest running sequence of tasks required to complete a project. For example, given the following tasks:
- Task A takes 1 hour.
- Task B takes 2 hours.
- Task C takes 30 minutes.
- Task D takes 45 minutes.
If the tasks must be completed in alphabetical order, then the critical path is A-B-C-D. And, the project will be complete in 4.25 hours.
But, if you have a helper, and the tasks only need to start in alphabetical order, then the critical path is A-C-D. And, the project will complete in 2.25 hours.
- Elapsed Time 0:00 - You start task A. Your helper starts task B.
- Elapsed Time 1:00 - You finish task A. You start task C
- Elapsed Time 1:30 - You finish task C. You start task D.
- Elapsed Time 2:00 - Your helper finishes task B.
- Elapsed Time 2:15 - You finish task D.
But, what does an agile software developer need with an antiquated term like critical path? I was using it in the context of removing engineering work from a broader business process that could be completed faster if the other department involved could execute their tasks in parallel with engineering. So, there!
No spam, no sharing to third party. Only you and me.
Member discussion